
BESS, RADIX Engineered: Reducing Costs, Maximising Efficiency
RADIX was the preferred screw pile contractor to complete the full design, supply & installation of screw pile foundations, including structural steelwork, for SolarPro at their project in Budapest, Hungary
Services:
- Pre-construction survey & testing
- Foundation Design
- Supply & Installation of RDX EXT Screw Piles + Support Steelwork
Products:
- 112 no. RDX EXT 89mm x 4500mm Screw Piles
- Structural steel support steelwork

Overview
SolarPro’s preferred method of installation to reduce programme on site and hit key milestone dates
As the main EPC contractor, SolarPro required a fast and efficient foundation solution that would not be delayed due to inclement weather. A full design package was provided on completion of site testing plus the supply and installation of RADIX foundations and structural steelwork for HiTHIUM ESS Containers along with Kehua Tech PCS Units.
Consideration was also to be given to this being a live site. Health & Safety was paramount and employing RADIX Screw piles as their preferred solution ensured there were reduced traffic movements without the need to remove any spoils from site and minimising landfill impact.

Solution
80% reduction of time with installation of RADIX foundations over alternative methods
RADIX attended site late October 2024 to complete site survey and static load testing. All materials and test equipment were transported from our UK headquarters ahead of the RADIX team arriving on site. Site testing was completed withing 48hrs before returning to the UK to have the full design package completed.
On sign-off of design, production was completed in the UK of structural steelwork and transported to site along with RADIX Screw Piles. The team landed in Budapest early February 2025 and completed the entire installation of screw piles and steelwork within 4 days, allowing the client to install Battery and PCS units immediately.